How to Select the Correct Mooring Bollard Capacity

59 minutes ago
4 min read

Selecting the correct mooring bollard capacity is an important part of designing a safe and reliable berthing facility. For ports, jetties, wharves, terminals and other marine facilities in Malaysia, bollards must safely withstand the forces transferred through a vessel’s mooring lines and into the supporting structure.


Marine mooring bollards on a concrete berth for vessel mooring



The objective is to select a bollard type and rated capacity suited to the actual project conditions.


Understanding Mooring Bollard Capacity


Mooring bollard capacity represents the load that the bollard system is designed to resist under specified conditions. However, the bollard itself is only one part of the load path:



Each component must safely transfer the required design forces. A correctly rated bollard does not automatically provide an adequately designed mooring point if its anchoring system or supporting structure cannot resist the same loads.


ESC Steel Engineering Sdn Bhd offers cast iron and steel marine bollards in various sizes, grades and capacities. Its bollards are designed and manufactured with reference to international standards and guidelines including BS 6349 Part 4 and PIANC guidance.


Marine mooring bollard securing a vessel with mooring lines at a berth


Start with the Design Vessel and Site Conditions


The selection process begins with understanding the vessels expected to use the berth. Relevant parameters include vessel type, displacement or DWT, length overall, beam, draft, freeboard and mooring arrangement.


DWT can provide an indication of vessel scale, but it should not be treated as a direct measure of the required bollard capacity.


Environmental conditions are equally important. Wind, current, waves, swell and tidal variations can influence the forces acting on a moored vessel and the resulting loads on individual mooring points. These conditions should be evaluated using project-specific data and the applicable marine design criteria.  


Where a berth will accommodate several vessel classes, the mooring system should be assessed against the governing design condition.


Consider the Mooring Arrangement and Line Angles


The arrangement of head lines, stern lines, breast lines and spring lines determines how vessel forces are distributed between mooring points.


Bollard spacing, vessel fairlead locations and horizontal and vertical line angles can significantly affect the load transferred to an individual bollard. This is why bollard type and capacity should be considered together.


ESC Steel Engineering Sdn Bhd offers configurations including T-Head, T-Horn, Kidney, Cleat, Double Bitt, Single Bitt and Pillar bollards. Different configurations are suited to different line arrangements and operating requirements.


For example, the Malaysia product information notes that T-Head and T-Horn bollards can accommodate higher line-load angles than some Single Bitt and Kidney configurations, while Single Bitt bollards are particularly suited to applications involving larger tidal variations and steep mooring-line angles.



Red marine mooring bollards installed along a concrete berth with rubber fenders


Determine the Required Bollard Capacity


Once vessel characteristics, environmental forces and the mooring arrangement have been established, the resulting loads can be assessed to determine the demand at each mooring point.


The selected capacity should consider the governing mooring-line load, load distribution, horizontal and vertical force components, applicable design factors and the operating conditions specified for the berth.


ESC Steel recommends calculating mooring loads where possible rather than relying exclusively on approximate capacity guidelines. It also notes that adverse weather conditions may require increased bollard capacity.


The final bollard rating should therefore be based on project-specific engineering analysis and the applicable design requirements, rather than simply matching vessel tonnage to bollard capacity.


Mooring bollard load diagram showing line tension, line angle, and horizontal and vertical force components


Verify the Foundation and Anchoring System


Selecting the appropriate bollard capacity is only part of the design.


The anchor bolts, foundation and supporting quay, jetty, dolphin or deck must also be capable of transferring the design loads. Depending on the project, this may require checks for anchor tension and shear, concrete breakout, reinforcement, base-plate bearing and overall structural capacity.


This is particularly important when upgrading an existing berth. Replacing an existing bollard with a higher-capacity unit does not automatically increase the capacity of the complete mooring point. The existing anchoring and supporting structure must also be verified.



Material and Corrosion Protection


Mooring bollards operate in demanding marine environments where saltwater exposure, moisture, mechanical wear and corrosion can affect long-term performance.


Material selection and protective coating should therefore be considered alongside capacity and geometry.



Marine mooring bollard and mooring lines securing a cargo vessel at a port berth


Selecting Mooring Bollards for Projects in Malaysia


Marine system catalog Asia

Selecting the correct mooring bollard requires more than choosing a capacity based on vessel size. The design vessel, environmental conditions, mooring configuration, line geometry, anchoring system and supporting structure all contribute to the final selection.


ESC Steel Engineering Sdn Bhd supplies marine mooring bollards and marine fender systems as part of its range of marine and piling solutions in Malaysia. Its bollard range covers multiple configurations, materials and capacities for applications at jetties, wharves, berths, dolphins, ports and harbours.


Providing vessel information, berth drawings, environmental design conditions, required capacity and applicable design standards can help establish an appropriate bollard solution for the project.